Bharat Heavy Electricals Limited
Power Sector Eastern Region
ISO 9001:2008 & ISO 27001:2013 Certified Organisation

JantERmantER in Hindi





Vendor's Area

Lokpal & Lokayuktas Act 2013 (Formats)

Right to Information


BHEL Fraud Prevention Policy

Swachh Bharat Abhiyan at BHEL PSER

Awareness film on eye donation


MTPP Kanti (2 x 195 MW):
Steam blowing first stage has been successfully completed on 07/11/2015.

BCPL Lapetkata:
13.5 MW Steam Turbine Generator Synchronised on 04/11/2015.

Singareni Unit 2 (600 MW):
Turbine Box Up Completed on 03/11/2015.

IPCL Haldia:
200MT Generator Stator Lifted and placed on foundation on 02/11/2015.

IOCL Paradeep:
GT-1 Naptha Firing Achieved successfully on 30/10/2015 with all parameters normal.

MTPP Kanti Unit-4 (195 MW):
EDTA cleaning of Boiler has been successfully done on 12/10/2015.

NEEPCO Monarchak:
Steam Blowing of HRSG completed on 10/10/2015.

IOCL Paradeep:
STG-2 achieved full load of 30 MW on 05/10/2015.

IOCL Paradeep:
Safety Valve Floating of HRSG-1 completed successfully on 01/10/2015.

IOCL Paradeep:
Safety Valve Floating of HRSG-2 completed successfully on 26/09/2015.

IB Valley Unit-2 (660 MW):
First Column Erection of 1st Unit of Stage-II has been completed on 14/09/2015.

BRBCL Nabinagar Unit-1 (250 MW):
Chemical Cleaning of Boiler completed successfully on 13/09/2015.

OTPC Palatana:
Achieved highest plant load of 687 MW on 12/09/2015.

IOCL Paradeep:
Captive Power Plant Project Team has achieved Five Hundred Days LTI Free Operation at IOCL Paradip Refinery Project on 12/09/2015.

IPCL Haldia Unit-1 (150 MW):
Drainable Hydraulic Test of Boiler has been completed on 11/09/2015.

NEEPCO Monarchak:
GT Trial Run (14 days) of TGBPP has been completed successfully on 07/09/2015 with available loads.

Barauni(R&M) Unit-1 (110 MW):
Chemical Cleaning of Boiler with EDTA has been successfully completed on 05/09/2015

BRBCL Nabinagar Unit- 1 (250 MW):
Alkali Boil out of Unit-1 Boiler has been completed successfully on 04/09/2015.

NEEPCO Monarchak:
Alkali Boil Out of HRSG has been completed successfully on 30/08/2015.

NTPC Bongaigaon:
Site Achieved 1265 LTI free days 28/08/2015.

MTPP Kanti Unit-4 (195 MW):
Generator Stator of Unit 4 lifted and placed on its foundation successfully with two EOT cranes in tandem operation on 27/08/2015.

MTPP Kanti Unit-4 (195 MW):
Non drainable hydro test of Boiler no. 4 has been successfully completed on 25/08/2015 and protocol signed by NTPC.

MTPP Kanti Unit-4 (195 MW):
Boiler of Unit 4 has been lit up successfully on 23/08/2015.

BRBCL Nabinagar Unit-1 (250 MW):
Lub oil flushing for STG at site started on 14/08/15 in presence of Sr Officials of BHEL and BRBCL.

BRBCL Nabinagar Unit-1 (250 MW):
Generator rotor threading has been successfully completed on 11/08/2015 in presence of Sr officials of BRBCL and BHEL.

Singereni Unit-2 (600 MW):
Ceremonial Boiler Light Up done by CMD-SCCL on 06/08/2015 with 4 Nos oil gun.

Singareni Unit-1 (600 MW):
Turbine Lub Oil Flushing Started on 06/08/2015.

Singereni Unit-2 (600 MW):
Boiler light up was successfully done on 03/08/2015.

IOCL Paradeep:
Captive Power Plant Project Team has achieved 5 million LTI free man-hours operation as on 31/07/2015.

Singereni Unit-1 (600 MW):
Turbine Box Up (LP - 2) completed on 31/07/2015.

Barauni R&M Unit-7 ():
Boiler light up has been successfully conducted on 25/07/2015.

Singareni Unit-2 (600 MW):
NDHT completed on 25/07/2015.

Site has successfully erected HP Boiler drum on 11/07/2015.

Singareni Unit-1 (600 MW):
LP Turbine Box Up done on 04/07/2015.

Singareni Unit-1 (600 MW):
Boiler was lighted up for the first time on 01/07/2015.

Surtagarh Unit-8 (660 MW):
Condensor Erection work started at Suratgarh Site on 28/06/2015.

IOCL Paradeep:
Steam Blowing of HRSG 2 has been successfully completed on 27/06/2015.

OTPC Palatana:
Highest Station Load of Palatana achieved 568 MW at gas flow of 110321 SMC/hr on 27/06/2015. This is the maximum corrected gas flow from ONGC till date.

NTPC Bongaigaon Unit-1 (250 MW):
Synchronisation and Full Load was achieved on 22/06/2015.

IOCL Paradeep:
Captive Power Plant Project Team has achieved one year LTI Free Operation at IOCL Paradip Refinery Project on 30/04/2015. In this process, more than 4 million safe man-hours operation have been achieved.

OIL Duliajan (20 MW):
Gas based Power Plant inaugurated on 15/04/2015.

Bokaro A (500 MW):
Synchronised successfully on 31/03/2015

Muzaffarpur Kanti Unit 3 (195 MW):
Full load achieved on 31/03/2015.

Sagardighi Unit 3 (500 MW):
Successfully Oil Synchronised on 31/03/2015.

Marwa Unit 2 (500 MW):
Synchronised successfully on 31/03/2015

NEEPCO Monarchak:
GT Full Load Achieved on 30/03/2015.

OTPC Palatana Power Block 2:
Commercial Opertaion of Power Block 2 declared from 24/03/2015. Unit is running at Full Load.

Bharat Heavy Electricals Limited,is, today, the largest engineering and manufacturing enterprise of its kind in India, with a well recognized track record of performance and profit making organization. The company's inherent potential coupled with its strong performance over the years, has resulted in being chosen as one of the Maharatna Public Sector Enterprises, which would enjoy support from the Government in their endeavors to become global players.

Power Sector-Eastern Region (PSER) of Bharat Heavy Electricals Ltd., is the Eastern Wing of company's Power Sector, with its head office at Kolkata, catering its services to the eastern part of India. The states which are being covered are Bihar, Jharkhand, Chhattisgarh, Orissa, West Bengal, Assam, Manipur, Meghalaya, Mizoram, Arunachal Pradesh, Nagaland, Tripura and Sikkim. Apart from the above, PSER has now crossed the barrier of conventional boundaries and is executing projects in the states of Andhra Pradesh, Telengana and Rajasthan as well. The Service group is engaged in overhauling and trouble shooting of different technical problems of power stations

Hindi Section                            Hindi Family


Bharat Heavy Electricals Limited
Power Sector : Eastern Region
Plot No DJ - 9/1, Sector II, Karunamoyee , Salt Lake City , Kolkata- 700 091, India
Registered Office: BHEL House, Siri Fort, New Delhi - 110049

Last Updated on: 12/11/2015