MAJOR HIGHLIGHTS OF PSER

SCCL Singareni Unit-2 (600 MW):
Full Load achieved on 25/11/2016.

IPCL Haldia Unit-1 (150 MW):
EDTA cleaning of Boiler successfully completed on 06/11/2016.

IPCL Haldia Unit-1 (150 MW):
Non-Drainable Hydro Test of Boiler successfully done on 19/10/2016.

BRBCL Nabinagar Unit-2 (250 MW):
Acid Cleaning successfully completed on 16/10/2016.

Punatsangchhu - I HEP Unit-2 (200 MW):
Final HV Test of Generator-Stator successfully completed on 15/10/2016.

Sagardighi Unit 4 (500 MW):
Synchronized successfully on 15/10/2016.

Punatsangchhu - I HEP Unit-1 (200 MW):
Final HV Test of Generator Stator successfully completed on 02/10/2016.

BRBCL Nabinagar Unit 2 (250 MW):
Boiler lighted up successfully 02/10/2016.

Mangedechu HEP Unit 1 (180 MW):
Distributor Hydro testing done successfully on 01/10/2016.

SCCL Singareni Unit-1 (600 MW):
Initial Operation (72 Hrs) completed on 25/09/2016.

BRBCL Nabinagar Unit-3 (250 MW):
Stator of TG was lifted and successfully placed on its foundation on 16/09/2016.

IPCL Haldia Unit-2 (150 MW):
Final Drainable Hydro Test of Boiler successfully demonstrated on 16/09/2016.

APGCL Namrup:
Gas Booster Compressor 1 commissioned on 07/09/2016

HNPCL Vizag Unit-1 (520 MW):
Successful completion of initial operation (720 hrs.) on 05/09/2016.

IPCL Haldia Unit-1 (150 MW):
Lube Oil Flushing of TG started at from 29/08/2016

Teesta Unit - 4 (40 MW):
Synchronization & Full load achieved on 11/08/2016.

SCCL Singareni (2 x 600 MW):
TPP was successfully Dedicated to the Nation on 07/08/2016 by the Honourable Prime Minister of India, Shri Narendra Modi.

APGCL Namrup:
GT cranked on 07/08/2016.

NTPC Bongaigaon Unit-2 (250 MW):
Non drainable Hydraulic Test has been completed on 05/08/2016.

North Karanpura Unit-2 (660 MW):
Boiler Erection started on 27/07/2016.

Marwa Unit-2 (500 MW) :
Full Load Achieved on 15/07/2016.

North Karanpura Unit-1 (660 MW):
Chimney Slipping started from 14/07/2016.

IOCL Paradip UB-4 :
Safety valve floating successfully completed on 05/07/2016.

Teesta Unit-3 (40 MW):
Full Load achieved on 03/07/2016.

HNPCL Vizag Unit-2 (520 MW):
COD declared on 02/07/2016.

Sagardighi Unit-3 (500 MW):
COD declared on on 01/07/2016.

Teesta Unit-3 (40 MW):
Synchronization successfully done on 01/07/2016.

North Karanpura Unit-1 (660 MW):
ESP Erection started on 29/06/2016.

North Karanpura Unit-3 (660 MW):
TG Raft Casting successfully completed on 26/06/2016.

Teesta Unit-4 (40 MW):
Rotor Assembly was lowered in pit successfully on 28/06/2016.

Teesta Unit-3 (40 MW):
Unit spun and rated speed of 125 rpm achieved on 27/06/2016. Bearing run completed on 28/06/2016.

SCCL Singareni Unit-1 (600 MW):
Fuel Oil Support withdrawal achieved on 09/06/2016.

Teesta Unit-4 (40 MW):
Turbine Assembly was lowered in pit successfully on 08/06/2016.

SCCL Singareni Unit-2 (600 MW):
Synchronisation completed on 28/05/2016.

BRBCL Nabinagar Unit-2 (250 MW):
Non drainable Hydro Test completed on 21/05/2016.

IOCL Paradip HRSG-2:
Full Load achieved on 19/05/2016 with FG Supplementary Firing.

North Karanpura Unit-2 (660 MW):
TG Raft casting successfully completed on 06/05/2016.

OTPC Palatana Power Block-2:
PG Test completed on 05/05/2016.

NTPC Bongaigaon Unit-2 (250 MW):
EDTA Chemical cleaning completed successfully on 04/05/2016.

IB Valley Unit-4 (660 MW):
First Ceiling Girder of Boiler successfully erected on 02/05/2016.

IB Valley Unit-3 (660 MW):
First Ceiling Girder of Boiler successfully erected on 22/04/2016.

Teesta Unit-3 (40 MW):
Rotor Assembly was successfully lowered in pit on 19/04/2016.

Teesta Unit-3 (40 MW):
Turbine Assembly was lowered in pit successfully on 08/04/2016.

IPCL Haldia Unit-1 (150 MW):
Turbine Box Up successfully achieved on 31/03/2016.

HNPCL Vizag Unit-2 (520 MW):
Synchronization and Full Load achieved on 31/03/2016.

NTPC Bongaigaon Unit-2 (250 MW):
Boiler lighted up on 27/03/2016.

NTPC Bongaigaon Unit-1 (250 MW):
COD declared after completion of 72 hrs full load operation on 26/03/2016.

Muzaffarpur Kanti Unit-2 (195 MW):
Synchronization and Full Load achieved on 24/03/2016.

Bokaro A (500 MW):
Full Load achieved on 22/03/2016.

BRBCL Nabinagar Unit-1 (250 MW):
Synchronization and Full Load achieved on 20/03/2016.

IOCL Paradip UB-4:
Steam Blowing successfully completed on 19/03/2016.

BCPL Lapetkata:
PG Test of GT-1 & HRSG-1 successfully conducted on 18/03/2016.

Teesta Unit-2 (40 MW):
Synchronization and Full Load achieved on 17/03/2016.

Suratgarh Unit-8 (660 MW):
Drainable Hydro Test of boiler successfully completed on 15/03/2016.

SCCL Singareni Unit-1 (600 MW):
Synchronization and Full Load achieved on 13/03/2016.

Sagardighi Unit-4 (500 MW):
EDTA cleaning with super heater back wash successfully completed on 13/03/2016.

IB Valley Unit-3 (660 MW):
Condenser Erection started on 11/03/2016.

IOCL Paradip UB-4:
Passivation has been successfully completed on 04/03/2016.

APGCL Namrup:
Fr 6FA GT Put on Turning Gear on 01/03/2016.

Barauni (R&M) Unit-7 (110 MW):
Oil Synchronization done successfully on 28/02/2016.

IOCL Paradip UB-4:
Citric Acid Cleaning has been successfully completed on 23/02/2016.

Sagardighi Unit 4 (500 MW):
First Light Up Of Boiler has been done successfully on 19/02/2016.

Barh Unit-5 (660 MW):
COD Declared On 18/02/2016.

BCPL Lapetketa STG (15 MW):
Full Loading achieved on 17/02/2016.

Teesta Unit-1 (40 MW):
Synchronized successfully on 14/02/2016 and achieved Full Load successfully.

IOCL Paradip UB-4:
ABO is successfully completed on 11/02/2016.

Barh Unit-5 (660 MW):
Unit has successfully completed 72 Hrs Full Load Run on 08/02/2016.

BRBCL Nabinagar Unit-1 (250 MW):
TG was successfully put on Barring Gear on 08/02/2016.

Teesta Unit-2 (40 MW):
Spinning Done successfully on 29/01/2016.

SCCL Singareni Unit-2 (600 MW):
Boiler Citric Acid Cleaning completed on 22/01/2016.

BRBCL Nabinagar Unit-1 (250 MW):
Steam Blowing has been completed successfully on 22/01/2016.

IOCL Paradip HRSG-1:
Achievement of Supplementary Firing successfully on 21/01/2016.

IPCL Haldia Unit-3 (150 MW):
Boiler Drum Lifted Successfully on 14/01/2016.

NEEPCO Monarchak:
Plant Full Load Achieved on 14/01/2016.

HNPCL Vizag Unit-1 (520 MW):
COD declared on 10/01/2016.

Muzaffarpur Kanti Unit-4 (195 MW):
Turbine Boxed Up on 09/01/2016.

BRBCL Nabinagar Unit-1 (250 MW):
Second Stage of Steam Blowing completed successfully on 08/01/2016.

Barauni (R&M) Unit-7 (110 MW):
Steam Blowing of Boiler & Piping has been successfully completed in 4 Stages on 08/01/2016 .

SCCL Singareni Unit-1 (600 MW):
Steam Blowing has hbeen completed successfully on 05/01/2016.

Sagardighi Unit-4 (500 MW):
Non Drainable Hyrdo Test of Boiler has been completed successfully on 05/01/2016.

SCCL Singareni Unit-2 (600 MW):
TG Deck Floating done on 01/01/2016.

Suratgarh Unit-7 (660 MW):
Drainable Hydraulic Test of Boiler has been successfully conducted on 31/12/2015.

SCCL Singareni Unit-1 (600 MW):
TG was put on barring gear for the first time on 27/12/2015.

IOCL Paradip UB-4:
Boiler light up successfully achieved on 23/12/2015.

SCCL Singareni Unit-1 (600 MW):
Steam blowing started with effect from 20/12/2015.

BRBCL Nabinagar Unit-1 (250 MW):
First phase steam blowing of boiler started on 18/12/2015.

OIL Duliajan (20 MW):
PG test of GTG completed successfully on 17/12/2015.

Sagardighi Unit-3 (500 MW):
Unit was inaugurated by Honourable Chief minister of West Bengal, Smt. Mamata Banerjee, on 16/12/2015.

Sagardighi Unit-3 (500 MW):
Full loading has been achieved on 14/12/2015.

Muzaffarpur Kanti Unit-4 (195 MW):
Oil flushing of turbine has been started with effect from 08/12/2015.

North Karanpura Unit-1 (660 MW):
PCC of TG Raft started on 07/12/2015.

HNPCL Vizag Unit-1 (520 MW):
Synchronized & Full Load achieved on 06/12/2015.

IOCL Paradip UB-2:
Refinery fuel gas firing achieved successfully on 05/12/2015.

IOCL Paradip UB-1 & UB-2:
Achievement of full loading successfully completed on 04/12/2015 with all parameters normal.

IOCL Paradip GT-2:
Naphtha firing achieved successfully on 02/12/2015 with all parameters normal.

IB Valley Unit-4 (660 MW):
ESP first column erection has been started on 01/12/2015.

IOCL Paradip UB-4:
Pre-boiler flushing has been completed successfully on 26/11/2015.

Muzaffarpur Kanti Unit-4 (195 MW):
Steam Blowing completed successfully on 24/11/2015 successfully.

Suratgarh Unit-7 (660 MW):
Stator lifted and safely placed on assembly stool at 17 M floor on 24/11/2015.

SCCL Singareni Unit-2 (600 MW):
Turbine Lube Oil Flushing started on 19/11/2015.

SCCL Singareni Unit-1 (600 MW):
Boiler Acid Cleaning completed on 14/11/2015.

BCPL Lapetkata:
13.5 MW Steam Turbine Generator Synchronised on 04/11/2015.

SCCL Singareni Unit-2 (600 MW):
Turbine Box Up Completed on 03/11/2015.

IPCL Haldia:
200 MT Generator Stator Lifted and placed on foundation on 02/11/2015.

IOCL Paradeep:
GT-1 Naptha Firing Achieved successfully on 30/10/2015 with all parameters normal.

Muzaffarpur Kanti Unit-4 (195 MW):
EDTA cleaning of Boiler has been successfully done on 12/10/2015.

NEEPCO Monarchak:
Steam Blowing of HRSG completed on 10/10/2015.

IOCL Paradip:
STG-2 achieved full load of 30 MW on 05/10/2015.

IOCL Paradip:
Safety Valve Floating of HRSG-1 completed successfully on 01/10/2015.

IOCL Paradip:
Safety Valve Floating of HRSG-2 completed successfully on 26/09/2015.

IB Valley Unit-2 (660 MW):
First Column Erection of 1st Unit of Stage-II has been completed on 14/09/2015.

BRBCL Nabinagar Unit-1 (250 MW):
Chemical Cleaning of Boiler completed successfully on 13/09/2015.

OTPC Palatana:
Achieved highest plant load of 687 MW on 12/09/2015.

IOCL Paradip:
Captive Power Plant Project Team has achieved Five Hundred Days LTI Free Operation at IOCL Paradip Refinery Project on 12/09/2015.

IPCL Haldia Unit-1 (150 MW):
Drainable Hydraulic Test of Boiler has been completed on 11/09/2015.

NEEPCO Monarchak:
GT Trial Run (14 days) of TGBPP has been completed successfully on 07/09/2015 with available loads.

Barauni(R&M) Unit-7 (110 MW):
Chemical Cleaning of Boiler with EDTA has been successfully completed on 05/09/2015

BRBCL Nabinagar Unit-1 (250 MW):
Alkali Boil out of Unit-1 Boiler has been completed successfully on 04/09/2015.

NEEPCO Monarchak:
Alkali Boil Out of HRSG has been completed successfully on 30/08/2015.

NTPC Bongaigaon:
Site Achieved 1265 LTI free days 28/08/2015.

Muzaffarpur Kanti Unit-4 (195 MW):
Generator Stator lifted and placed on its foundation successfully with two EOT cranes in tandem operation on 27/08/2015.

Muzaffarpur Kanti Unit-4 (195 MW):
Non drainable hydro test of Boiler successfully completed on 25/08/2015 and protocol signed by NTPC.

Muzaffarpur Kanti Unit-4 (195 MW):
Boiler of Unit 4 has been lit up successfully on 23/08/2015.

BRBCL Nabinagar Unit-1 (250 MW):
Lub oil flushing for STG at site started on 14/08/15 in presence of Sr. Officials of BHEL and BRBCL.

BRBCL Nabinagar Unit-1 (250 MW):
Generator rotor threading has been successfully completed on 11/08/2015 in presence of Sr officials of BRBCL and BHEL.

SCCL Singareni Unit-2 (600 MW):
Ceremonial Boiler Light Up done by CMD-SCCL on 06/08/2015 with 4 Nos oil gun.

SCCL Singareni Unit-1 (600 MW):
Turbine Lub Oil Flushing Started on 06/08/2015.

SCCL Singareni Unit-2 (600 MW):
Boiler light up was successfully done on 03/08/2015.

IOCL Paradip:
Captive Power Plant Project Team has achieved 5 million LTI free man-hours operation as on 31/07/2015.

SCCL Singareni Unit-1 (600 MW):
Turbine Box Up (LP - 2) completed on 31/07/2015.

Barauni R&M Unit-7 ():
Boiler light up has been successfully conducted on 25/07/2015.

SCCL Singareni Unit-2 (600 MW):
NDHT completed on 25/07/2015.

APGCL Namrup:
Site has successfully erected HP Boiler drum on 11/07/2015.

SCCL Singareni Unit-1 (600 MW):
LP Turbine Box Up done on 04/07/2015.

SCCL Singareni Unit-1 (600 MW):
Boiler was lighted up for the first time on 01/07/2015.

Surtagarh Unit-8 (660 MW):
Condenser Erection work started at Suratgarh Site on 28/06/2015.

IOCL Paradip:
Steam Blowing of HRSG 2 has been successfully completed on 27/06/2015.

OTPC Palatana:
Highest Station Load achieved 568 MW at gas flow of 110321 SMC/hr on 27/06/2015. This is the maximum corrected gas flow from ONGC till date.

NTPC Bongaigaon Unit-1 (250 MW):
Synchronisation and Full Load achieved on 22/06/2015.

IOCL Paradip:
Captive Power Plant Project Team has achieved one year LTI Free Operation on 30/04/2015. In this process, more than 4 million safe man-hours operation have been achieved.

OIL Duliajan (20 MW):
Gas based Power Plant inaugurated on 15/04/2015.

Bokaro A (500 MW):
Synchronised successfully on 31/03/2015

Muzaffarpur Kanti Unit-3 (195 MW):
Full load achieved on 31/03/2015.

Sagardighi Unit-3 (500 MW):
Successfully Oil Synchronised on 31/03/2015.

Marwa Unit-2 (500 MW):
Synchronised successfully on 31/03/2015

NEEPCO Monarchak:
GT Full Load Achieved on 30/03/2015.

OTPC Palatana Power Block-2:
Commercial Operation of Power Block 2 declared from 24/03/2015. Unit running on Full Load.


Bharat Heavy Electricals Limited, is, today, the largest engineering and manufacturing enterprise of its kind in India, with a well recognized track record of performance and profit making organization. The company's inherent potential coupled with its strong performance over the years, has resulted in being chosen as one of the Maharatna Public Sector Enterprises, which would enjoy support from the Government in their endeavours to become global players.


Power Sector-Eastern Region (PSER) of Bharat Heavy Electricals Ltd., is the Eastern Wing of company's Power Sector, with its head office at Kolkata, catering its services to the eastern part of India. The states which are being covered are Bihar, Jharkhand, Chhattisgarh, Odisha, West Bengal, Assam, Manipur, Meghalaya, Mizoram, Arunachal Pradesh, Nagaland, Tripura and Sikkim. Apart from the above, PSER has now crossed the barrier of conventional boundaries and is executing projects in the states of Andhra Pradesh, Telengana and Rajasthan as well. The Service group is engaged in overhauling and trouble shooting of different technical problems of power stations





OUR CUSTOMERS: CSEB--DVC--NTPC--BRBCL--WBPDCL--DPL--KBUNL--HNPCL--BSEB--SCCL--RVUNL--OPGCL--OTPC-- ABHIJIT--APNRL--TSPCL--CSPGCL--APGCL--TATA POWER--NEEPCO--IOCL--IISCO--BRPL--OIL-- BCPL--NHPC--NPGCL-BIFPCL



Bharat Heavy Electricals Limited
Power Sector : Eastern Region
Plot No DJ - 9/1, Sector II, Karunamoyee , Salt Lake City , Kolkata- 700091, India
Registered Office: BHEL House, Siri Fort, New Delhi - 110049

Last Updated on: 30/11/2016