JantERmantER

Bharat Heavy Electricals Limited
Power Sector Eastern Region (PSER)
ISO 9001:2015 & ISO 27001:2013 Certified Organisation

WELCOME TO BHEL PSER's INTERNET SITE

JantERmantER in Hindi

DISCONTINUATION OF PRACTICE OF PUBLICATION OF TENDER ADVERTISEMENTS IN NEWSPAPERS

CONTENTS

BHEL ANTHEM (Track 1)

BHEL ANTHEM (Track 2)

Vendor's Area

Lokpal & Lokayuktas Act 2013 (Formats)

Right to Information

NOTICE BOARD

BHEL Fraud Prevention Policy

Swachh Bharat Abhiyan at BHEL PSER

Awareness film on eye donation

HINDI SECTION

Hindi Section

Hindi Parivar

   
MAJOR HIGHLIGHTS OF PSER 2018-19

OPGCL IB Valley (2 x 660 MW) :
Unit 3 TG & Unit 4 TG has been put on Barring gear at 17:05 Hrs & 17:25 Hrs respectively on 09/10/2018. Both TG has been put on Barring gear on the same day.

BRBCL Nabinagar Unit-1 (250 MW):
SG PG Test completed successfully on 08/10/2018.

Punatsangchhu-2 HEP :
Assembly and Hydro Test of 1st Butter Fly (BF) valve successfully completed on 08/10/2018.

RRVUNL Suratgarh Unit-8 (660 MW) :
Boiler Alkali Flushing and Acid cleaning (including Rinsing) Started on 29/09/2018 and successfully completed on 06/10/2018.

OPGCL IB Valley (2 x 660 MW) :
TG Oil flushing of both units completed successfully, Unit-3 completed on 03/10/2018 & Unit-4 completed on 05/10/2018.

BRBCL Nabinagar Unit-1 (250 MW) :
PG Test of TG Cycle completed during the period 30/09/2018 to 04/10/2018.

BRBCL Nabinagar Unit-3 (250 MW) :
Boiler acid cleaning successfully completed on 03/10/2018.

Punatsangchhu - I Unit-5 (200 MW) :
Core Flux Test of Stator completed successfully on 03/10/2018 with Core Loss observed within permissible [design] limit & no Hot Spot detected for the Stator during the test.

Tata Steel Jamshedpur (40 MW):
Oil Flushing completed on 26/09/2018

OPGCL IB Valley Unit-4 (660 MW):
Chemical cleaning completed successfully on 15/09/2018.

BRBCL Nabinagar Unit-3 (250 MW) :
BLU achieved successfully on 13/09/2018.

NTPC Bongaigaon Unit-3 (250 MW) :
Steam Blowing completed on 10/09/2018.

NSPCL Rourkela (250 MW):
Boiler Drainable Hydro Test successfully completed on 08/09/2018.

BRBCL Nabinagar Unit-3 (250 MW):
TG Deck floating activity successfully completed on 06/09/2018.

OPGCL IB Valley Unit-4 (660 MW) :
Boiler Light Up successfully completed on 31/08/2018.

Punatsangchhu-1 HEP:
Hydro test of 2nd MIV successfully completed on 26/08/2018. Assembly and testing of this MIV has been completed in record time of 26 days as against L2 schedule of 40 days.

RRVUNL Suratgarh Unit-7 (660 MW):
Steam Blowing successfully completed on 25/08/2018.

OPGCL IB Valley Unit-4 (660 MW):
MDBFP trial run done on 23/08/2018 for the 1st time after successful interlock protection.

RRVUNL Suratgarh Unit-8 (660 MW):
GT Charging completed on 21/08/2018.

Mangdechhu Unit-4 (180 MW) :
Stator has been lowered in generator barrel on 12/08/2018.

NTPC Bongaigaon Unit-3 (250 MW):
First stage of steam blowing completed on 06/08/2018.

OPGCL IB Valley Unit-4 (660 MW):
Auxiliary Boiler Alkali Boil out completed successfully on 04/08/2018.

IOCL Paradip:
PG test of GT-3 & HRSG-3 completed on 01/08/2018.

OPGCL IB Valley Unit-4 (660 MW):
Non-Drainable Hydro Test of Boiler completed successfully on 17/07/2018 & Main Steam Line Hydro Test on 28/07/2018.

RRVUNL Suratgarh Unit-8 (660 MW):
Non-Drainable Hydraulic Test of Boiler Super Heater circuit completed successfully at pressure of 436 Kg sq cm on 27/07/2018.

RRVUNL Suratgarh Unit-8 (660 MW):
Non-Drainable Hydraulic Test of Boiler Re-Heater circuit successfully completed at pressure of 110 Kg sq cm on 27/07/2018.

NTPC Bongaigaon Unit-3 (250 MW):
TG Barring gear achieved on 26/07/2018.

OPGCL IB Valley (2 x 660 MW):
Auxiliary boiler light up done successfully on 26/07/2018.

BRBCL Nabinagar Unit-3 (250 MW):
STG Lub Oil, Seal Oil and Control Oil flushing completed successfully on 26/07/2018.

RRVUNL Suratgarh Unit-8 (660 MW):
Pre-Boiler detergent flushing (comprising of boiler feed water, condensate and HP-LP drip pipelines) along with rinsing & passivation completed successfully on 23/07/2018 in presence of Senior RRVUNL and BHEL officials.

Maitree Bangladesh Unit-1 (660 MW):
Boiler Erection started on 30/06/2018.

BRBCL Nabinagar Unit-3 (250 MW):
Detergent flushing phase I, II, III completed successfully on 13/06/2018.

RVUNL Suratgarh Unit-7 (660MW):
Steam Blowing started on 09/06/2018.

Mangdechhu Unit-3 (180 MW):
Rotor lowered on 09/06/2018.

KBUNL Muzaffarpur Unit 4 (195 MW):
Trial Run completed on 07/03/2018, Certificate received on 31/05/2018.

Tata Steel Jamshedpur (40 MW):
Turbine Boxed Up on 22/05/2018.

Marwa Unit-1 (500 MW):
PG test of Boiler package successfully completed on 19/05/2018.

IISCO Burnpur:
PG test of Boiler-3 (200TPH) successfully completed 04/05/2018.

Punatsangchhu-1 Unit-2 (200 MW):
Lowering of Generator Stator successfully done on its foundation on 03/05/2018.

RVUNL Suratgarh Unit-7 (660 MW):
Alkali Boil Out and Chemical Cleaning of Boiler along with passivation & rinsing completed successfully on 30/04/2018.

Maitree Bangladesh Unit-2 (660 MW):
Foundation work of Boiler started on 23/04/2018.

NTPC Bongaigaon Unit-1 (250 MW):
Milling System PG Test completed on 06/04/2018.

NTPC Bongaigaon Unit-3 (250 MW):
BFD System Hydro Test completed on 03/04/2018.


Bharat Heavy Electricals Limited, is, today, the largest engineering and manufacturing enterprise of its kind in India, with a well recognized track record of performance and profit making organization. The company's inherent potential coupled with its strong performance over the years, has resulted in being chosen as one of the Maharatna Public Sector Enterprises, which would enjoy support from the Government in their endeavours to become global players.


Power Sector-Eastern Region (PSER) of Bharat Heavy Electricals Limited, is the Eastern Wing of the Company's Power Sector, with its head office at Kolkata, catering its services to the eastern part of India. The states which are being covered are Bihar, Jharkhand, Chhattisgarh, Odisha, West Bengal, Assam, Manipur, Meghalaya, Mizoram, Arunachal Pradesh, Nagaland, Tripura and Sikkim. Apart from the above, PSER has now crossed the barrier of conventional boundaries and is executing projects in the states of Andhra Pradesh, Telengana and Rajasthan as well. Add to that projects are also being executed outside India. The Service group is engaged in overhauling and trouble shooting of different technical problems of power stations.





OUR CUSTOMERS: CSEB--DVC--NTPC--BRBCL--WBPDCL--DPL--KBUNL--HNPCL--BSEB--SCCL--RVUNL--OPGCL--OTPC-- ABHIJIT--APNRL--TSPCL--CSPGCL--APGCL--TATA POWER--NEEPCO--IOCL--IISCO--BRPL--OIL-- BCPL--NHPC--NPGCL--BIFPCL



Bharat Heavy Electricals Limited
Power Sector : Eastern Region
Plot No DJ - 9/1, Sector II, Karunamoyee , Salt Lake City , Kolkata- 700091, India
Registered Office: BHEL House, Siri Fort, New Delhi - 110049

Last Updated on: 15/10/2018