JantERmantER

Bharat Heavy Electricals Limited
Power Sector Eastern Region
ISO 9001:2008 & ISO 27001:2013 Certified Organisation

JantERmantER in Hindi

WELCOME TO BHEL PSER's INTERNET SITE

CONTENTS

BHEL ANTHEM (Track 1)

BHEL ANTHEM (Track 2)

Vendor's Area

Lokpal & Lokayuktas Act 2013 (Formats)

Right to Information

NOTICE BOARD

BHEL Fraud Prevention Policy

Swachh Bharat Abhiyan at BHEL PSER

Awareness film on eye donation

HINDI SECTION

Hindi Section

Hindi Family

   
MAJOR HIGHLIGHTS OF PSER 17-18

NEEPCO Tuirial HEP Unit-2 (30 MW):
Unit spun on 17/11/2017 at rated speed of 230 RPM.

BSEB Barauni Unit-8 (250 MW):
Synchronization achieved on 14/11/2017.

RVUNL Suratgarh Unit-7 (660 MW):
Barring gear with speed 47 rpm accomplished on 09/11/2017.

NSPCL Rourkela (250 MW) :
Boiler drum lifting achieved on 04/11/2017.

NTPC Bongaigaon Unit-2 (250 MW) :
COD declared at 00:00 hrs on 01/11/2017.

NEEPCO Tuirial HEP Unit-1 (30 MW) :
Trial run successfully completed on 29/10/2017.

OPGCL IB Valley Unit-3 (660 MW) :
APH-3A Module erection completed in a record time by 20th day from start of Bottom Centre Section (Cold End) erection on 29/10/2017.

North Karanpura Unit-2 (660 MW) :
Ceiling Girder Erection of Boiler achieved on 25/10/2017.

North Karanpura Unit-3 (660 MW) :
Erection of Collecting Electrode started on 25/10/2017 for ESP Pass A.

IPCL Haldia Unit-2 (150 MW):
Turbine Box up achieved on 25/10/2017.

RVUNL Suratgarh (2 x 660 MW) :
Auxiliary Boiler Light-up, completed successfully on 07/10/2017.

Mangdechu Unit-1 (180 MW) :
Rotor successfully lowered inside barrel on 06/10/2017.

RVUNL Suratgarh Unit-8 (660 MW) :
Boiler Light Up achieved on 28/09/2017.

NPGCL Nabinagar Unit-1 (660 MW) :
Steam Blowing (1st stage) of Boiler started on 22/09/2017.

IPCL Haldia Unit 2 (150 MW) :
Steam Blowing Operation successfully completed on 16/09/2017.

BCPL Lepetkata :
PG Test of GT-2 & HRSG-2 has been successfully conducted on 15/09/2017.

BSEB Barauni Unit-8 (250 MW) :
Steam Blowing (all stages) completed successfully on 03/09/2017.

BRBCL Nabinagar Unit-2 (250 MW) :
COD completed successfully from 23:45 hrs. of 27/08/2017 to 23:45 hrs. of 30/08/2017 .

IPCL Haldia (3 x 150 MW) :
LTI free Days achieved at site - 1076 Days.

NTPC Bongaigaon (3 X 250 MW) :
LTI free days achieved at site - 1840 Days.

BSEB Barauni Unit-9 (250 MW) :
Boiler Light Up achieved successfully on 29/08/2017.

NEEPCO Tuirial HEP Unit-1 (30 MW) :
Full load achieved on 25/08/2017.

Barauni R&M Unit-6 (110 MW) :
TG oil flushing started on 20/08/2017.

Barauni R&M Unit-6 (110 MW) :
Chemical Cleaning of Boiler with EDTA successfully completed on 19/08/2017.

NEEPCO Tuirial HEP Unit-1 (30 MW) :
Unit synchronised on 14/08/2017.

BSEB Barauni Unit-9 (250 MW) :
Non Drainable Hydro Test conducted successfully on 10/08/2017.

BSEB Barauni Unit-8 (250 MW):
Steam Blowing started on 08/08/2017.

NPGCL Nabinagar Unit-1 (660 MW):
Chemical cleaning of Boiler successfully completed on 02/08/2017.

BSEB Barauni Unit-8 (250 MW):
Hydro test of Re-heater done on 01/08/2017.

IOCL Paradip:
PG Test of GTG-1 & HRSG-1 completed on 30/07/2017.

BSEB Barauni Unit-8 (250 MW):
Hydro test of MS pipe done on 25/07/2017.

NPGCL Nabinagar Unit-1 (660 MW):
Boiler light up achieved on 16/07/2017.

NEEPCO Tuirial Unit-1 (30 MW):
Successfully spun up to rated speed on 15/07/2017.

IPCL Haldia Unit 2 (150 MW):
All the four guns of AB elevation got proven for the first time, Boiler in presence of customer Higher Authority on 10/07/2017.

IOCL Paradip:
PG Test of GTG-2 & HRSG-2 completed on 09/07/2017.

NPGCL Nabinagar (3 x 660 MW):
Hydro test of entire re-heater circuit done on 04/07/2017 at pressure 106.5 kg / sq. cm.

NTPC Bongaigaon Unit-3 (250 MW):
Boiler light up achieved on 01/07/2017.

NSPCL Rourkela (250 MW):
TG Raft Casting achieved on 28/06/2017.

BSEB Barauni Unit-8 (250 MW):
Pre Boiler flushing achieved successfully on 22/06/2017.

NEEPCO Kameng Unit-3 (150 MW):
Stator Assembly having total weight of 252 MT was successfully lowered in pit on 21/06/2017.

BSEB Barauni Unit-8 (250 MW):
Barring Gear achieved successfully on 20/06/2017.

NEEPCO Tuirial Unit-1 (30 MW):
Unit Box up and alignment achieved on 20/06/2017.

NEEPCO Kameng Unit-3 (150 MW):
HV Test of stator completed successfully at 29.5 KV on 18/06/2017 at 01:25 PM.

BSEB Barauni Unit-8 (250 MW):
Boiler Light up achieved on 18/06/2017.

North Karanpura Unit-2 (660 MW):
Erection of Collecting Electrode at ESP Pass B started on 12/06/2017.

IPCL Haldia Unit-1 (150 MW):
Full Load achieved on 07/06/2017.

RRUVNL Suratgarh Unit-8 (660 MW):
Boiler High pressure BFD line Hydro Test achieved successfully at 532 kg / sq. cm on 06/06/2017.

BSEB Barauni Unit-8 (250 MW):
Non-Drainable Hydro Test (NDHT) of Boiler conducted successfully at 274 kg / sq. cm pressure on 05/06/2017.

RUVNL Suratgarh Unit-7 (660 MW):
Hydro Test of Main Steam Line completed successfully on 31/05/2017.

NPGCL Nabinagar Unit-1 (660 MW):
Hydro Test of Main Steam Line completed successfully on 16/05/2017.

NPGCL Nabinagar (3 x 660 MW):
Auxiliary Boiler Light up achieved successfully on 11/05/2017.

North Karanpura Unit-3 (660 MW):
ESP Erection started on 28/04/2017.

North Karanpura Unit-2 (660 MW):
TG deck casting completed on 24/04/2017.

North Karanpura Unit-1 (660 MW):
TG deck casting started on 12/04/2017.

NEEPCO Monarchak (101 MW):
14 days Trial Run including 72 hrs. full load operation completed successfully on 04/04/2017.

BRBCL Nabinagar Unit-2 (250 MW):
Full load achieved on 03/04/2017.

BCPL Lapetkata:
PG Test of STG successfully conducted on 03/04/2017.

BRBCL Nabinagar Unit-2 (250 MW):
Synchronisation achieved on 02/04/2017.


Bharat Heavy Electricals Limited, is, today, the largest engineering and manufacturing enterprise of its kind in India, with a well recognized track record of performance and profit making organization. The company's inherent potential coupled with its strong performance over the years, has resulted in being chosen as one of the Maharatna Public Sector Enterprises, which would enjoy support from the Government in their endeavours to become global players.


Power Sector-Eastern Region (PSER) of Bharat Heavy Electricals Limited, is the Eastern Wing of the Company's Power Sector, with its head office at Kolkata, catering its services to the eastern part of India. The states which are being covered are Bihar, Jharkhand, Chhattisgarh, Odisha, West Bengal, Assam, Manipur, Meghalaya, Mizoram, Arunachal Pradesh, Nagaland, Tripura and Sikkim. Apart from the above, PSER has now crossed the barrier of conventional boundaries and is executing projects in the states of Andhra Pradesh, Telengana and Rajasthan as well. Add to that projects are also being executed outside India. The Service group is engaged in overhauling and trouble shooting of different technical problems of power stations.





OUR CUSTOMERS: CSEB--DVC--NTPC--BRBCL--WBPDCL--DPL--KBUNL--HNPCL--BSEB--SCCL--RVUNL--OPGCL--OTPC-- ABHIJIT--APNRL--TSPCL--CSPGCL--APGCL--TATA POWER--NEEPCO--IOCL--IISCO--BRPL--OIL-- BCPL--NHPC--NPGCL-BIFPCL



Bharat Heavy Electricals Limited
Power Sector : Eastern Region
Plot No DJ - 9/1, Sector II, Karunamoyee , Salt Lake City , Kolkata- 700091, India
Registered Office: BHEL House, Siri Fort, New Delhi - 110049

Last Updated on: 22/11/2017