JantERmantER

भारत हेवी इलेक्ट्रिकल्‍स लिमिटेड
पावर सेक्‍टर पूर्वी क्षेत्र
आई एस ओ 9001ः2008 एवं आइएसओ 27001ः2013 प्रमाणित संगठन

JantERmantER in English

बीएचईएल पीएसईआर के इंटरनेट पृष्‍ठ पर आपका स्‍वागत है

अंतर्वस्‍तु

भेलगीत (1 ट्रैक)

भेलगीत (2 ट्रैक)

वेंडर्स एरिया

लोकपाल एवं लोकायुक्‍त अधिनियम 2013 के तहत फॉर्मेट

सूचना का अधिकार

सूचना बोर्ड

बीएचईएल पीएसईआर में स्‍वच्‍छ भारत अभियान

चक्षु दान पर जागरूकता फैलाने वाली फिल्‍म

   
पीएसईआर के विशिष्‍ट कीर्तिमान

Suratgarh Unit-7 (660 MW):
Drainable Hydraulic Test of Boiler has been successfully conducted on 31/12/2015.

Singareni Unit-1 (600 MW):
TG was put on barring gear for the first time on 27/12/2015.

IOCL Paradeep UB-4:
Boiler light up successfully achieved on 23/12/2015.

Singareni Unit-1 (600 MW):
Steam blowing started with effect from 20/12/2015.

BRBCL Nabinagar Unit-1 (250 MW):
First phase steam blowing of boiler started on 18/12/2015.

OIL Duliajan (20 MW):
PG test of GTG completed successfully on 17/12/2015.

Sagardighi Unit-3 (500 MW):
Unit was inaugrated by Honorable Chief minister of West Bengal, Smt. Mamata Banerjee, on 16/12/2015.

Sagardighi Unit-3 (500 MW):
Full loading has been achieved on 14/12/2015.

MTPP Kanti Unit-4 (195 MW):
Oil flushing of turbine has been started with effect from 08/12/2015.

North Karanpura Unit-1 (660 MW):
PCC of TG Raft started on 07/12/2015.

HNPCL Vizag Unit-1 (520 MW):
Synchronized & Full Load achieved on 06/12/2015.

IOCL Paradeep UB-2:
Refinery fuel gas firing achieved successfully on 05/12/2015.

IOCL Paradeep UB-1 & UB-2:
Achievement of full loading successfully completed on 04/12/2015 with all parameters normal.

IOCL Paradeep GT-2:
Naphtha firing achieved successfully on 02/12/2015 with all parameters normal.

IB Valley Unit-4 (660 MW):
ESP first column erection has been started on 01/12/2015.

IOCL Paradeep UB-4:
Pre-boiler flushing has been completed successfully on 26/11/2015.

MTPP Kanti Unit-4 (195 MW):
Steam Blowing completed successfully on 24/11/2015 successfully.

Suratgarh Unit-7 (660 MW):
Stator lifted and safely placed on assembly stool at 17 M floor on 24/11/2015.

Singareni Unit-2 (600 MW):
Turbine Lube Oil Flushing started on 19/11/2015.

Singareni Unit-1 (600 MW):
Boiler Acid Cleaning completed on 14/11/2015.

BCPL Lapetkata:
13.5 MW Steam Turbine Generator Synchronised on 04/11/2015.

Singareni Unit-2 (600 MW):
Turbine Box Up Completed on 03/11/2015.

IPCL Haldia:
200MT Generator Stator Lifted and placed on foundation on 02/11/2015.

IOCL Paradeep:
GT-1 Naptha Firing Achieved successfully on 30/10/2015 with all parameters normal.

MTPP Kanti Unit-4 (195 MW):
EDTA cleaning of Boiler has been successfully done on 12/10/2015.

NEEPCO Monarchak:
Steam Blowing of HRSG completed on 10/10/2015.

IOCL Paradeep:
STG-2 achieved full load of 30 MW on 05/10/2015.

IOCL Paradeep:
Safety Valve Floating of HRSG-1 completed successfully on 01/10/2015.

IOCL Paradeep:
Safety Valve Floating of HRSG-2 completed successfully on 26/09/2015.

IB Valley Unit-2 (660 MW):
First Column Erection of 1st Unit of Stage-II has been completed on 14/09/2015.

BRBCL Nabinagar Unit-1 (250 MW):
Chemical Cleaning of Boiler completed successfully on 13/09/2015.

OTPC Palatana:
Achieved highest plant load of 687 MW on 12/09/2015.

IOCL Paradeep:
Captive Power Plant Project Team has achieved Five Hundred Days LTI Free Operation at IOCL Paradip Refinery Project on 12/09/2015.

IPCL Haldia Unit-1 (150 MW):
Drainable Hydraulic Test of Boiler has been completed on 11/09/2015.

NEEPCO Monarchak:
GT Trial Run (14 days) of TGBPP has been completed successfully on 07/09/2015 with available loads.

Barauni(R&M) Unit-1 (110 MW):
Chemical Cleaning of Boiler with EDTA has been successfully completed on 05/09/2015

BRBCL Nabinagar Unit-1 (250 MW):
Alkali Boil out of Unit-1 Boiler has been completed successfully on 04/09/2015.

NEEPCO Monarchak:
Alkali Boil Out of HRSG has been completed successfully on 30/08/2015.

NTPC Bongaigaon:
Site Achieved 1265 LTI free days 28/08/2015.

MTPP Kanti Unit-4 (195 MW):
Generator Stator of Unit 4 lifted and placed on its foundation successfully with two EOT cranes in tandem operation on 27/08/2015.

MTPP Kanti Unit-4 (195 MW):
Non drainable hydro test of Boiler no. 4 has been successfully completed on 25/08/2015 and protocol signed by NTPC.

MTPP Kanti Unit-4 (195 MW):
Boiler of Unit 4 has been lit up successfully on 23/08/2015.

BRBCL Nabinagar Unit-1 (250 MW):
Lub oil flushing for STG at site started on 14/08/15 in presence of Sr Officials of BHEL and BRBCL.

BRBCL Nabinagar Unit-1 (250 MW):
Generator rotor threading has been successfully completed on 11/08/2015 in presence of Sr officials of BRBCL and BHEL.

Singereni Unit-2 (600 MW):
Ceremonial Boiler Light Up done by CMD-SCCL on 06/08/2015 with 4 Nos oil gun.

Singareni Unit-1 (600 MW):
Turbine Lub Oil Flushing Started on 06/08/2015.

Singereni Unit-2 (600 MW):
Boiler light up was successfully done on 03/08/2015.

IOCL Paradeep:
Captive Power Plant Project Team has achieved 5 million LTI free man-hours operation as on 31/07/2015.

Singereni Unit-1 (600 MW):
Turbine Box Up (LP - 2) completed on 31/07/2015.

Barauni R&M Unit-7 ():
Boiler light up has been successfully conducted on 25/07/2015.

Singareni Unit-2 (600 MW):
NDHT completed on 25/07/2015.

Namrup:
Site has successfully erected HP Boiler drum on 11/07/2015.

Singareni Unit-1 (600 MW):
LP Turbine Box Up done on 04/07/2015.

Singareni Unit-1 (600 MW):
Boiler was lighted up for the first time on 01/07/2015.

Surtagarh Unit-8 (660 MW):
Condensor Erection work started at Suratgarh Site on 28/06/2015.

IOCL Paradeep:
Steam Blowing of HRSG 2 has been successfully completed on 27/06/2015.

OTPC Palatana:
Highest Station Load of Palatana achieved 568 MW at gas flow of 110321 SMC/hr on 27/06/2015. This is the maximum corrected gas flow from ONGC till date.

NTPC Bongaigaon Unit-1 (250 MW):
Synchronisation and Full Load was achieved on 22/06/2015.

IOCL Paradeep:
Captive Power Plant Project Team has achieved one year LTI Free Operation at IOCL Paradip Refinery Project on 30/04/2015. In this process, more than 4 million safe man-hours operation have been achieved.

OIL Duliajan (20 MW):
Gas based Power Plant inaugurated on 15/04/2015.

Bokaro A (500 MW):
Synchronised successfully on 31/03/2015

MTPP Kanti Unit-3 (195 MW):
Full load achieved on 31/03/2015.

Sagardighi Unit-3 (500 MW):
Successfully Oil Synchronised on 31/03/2015.

Marwa Unit-2 (500 MW):
Synchronised successfully on 31/03/2015

NEEPCO Monarchak:
GT Full Load Achieved on 30/03/2015.

OTPC Palatana Power Block-2:
Commercial Opertaion of Power Block 2 declared from 24/03/2015. Unit is running at Full Load.


भारत हेवी इलेक्ट्रिकल्स लिमिटेड भारत में आज अपने ही प्रकार का इंजीनियरी एवं उत्पादकता वाला बृहद्तम संगठन है। जिसे लाभ कमाऊ उद्यम एवं कार्यकारिता के लिए पहचाना जाता है। कम्पनी को वर्षों से उसकी सशक्त कार्यकारिता और सामर्थ्य के परिणामस्वरुप महारत्न कंपनियों में स्थान दिया गया है । इस उद्यम को विश्व बाजार में अपनी साख बनाने के लिए सरकार का पूरा-पूरा समर्थन प्राप्त है ।


भारत हेवी इलेक्ट्रिकल्स लिमिटेड, पावर सेक्टर-पूर्वी क्षेत्र कंपनी के पावर सेक्टर का पूर्वी स्‍कंध है,जिसका मुख्यालय कोलकाता है एवं भारत के पूर्वी क्षेत्र को सेवाएं प्रदान करता है । पूर्वी क्षेत्र के अंतर्गत बिहार , उड़ीसा , पश्चिम बंगाल , असम, मेघालय, मणिपुर, मिजोरम ,अरुणाचल प्रदेश,नागालैंड,त्रिपुरा एवं सिक्किम राज्य आते हैं । इसके अतिरिक्‍त पीएसईआर ने अब औपचारिक सीमाएं पार कर ली हैं एवं आंध्रप्रदेश, तेलंगाना तथा राजस्‍थान जैसे राज्‍यों में परियोजनाएं निष्‍पादित कर रहा है।



हिंदी अनुभाग                            हिंदी परिवार


हमारे ग्राहक-सीएसर्इबी – डीवीसी – एनटीपीसी-बीआरबीसीएल- डब्‍ल्‍यु बी पी डी सी एल – डीपीएल – केबीयुएनएल – एचएनपीसीएल बीएसईबी – एससीसीएल – आरवीयुएनएल – अीपीजीसीएल- ओटीपीसी- अभिजित – एपीएनआरएल – टीएसपीसीएल – सीएसपीजीसीएल – एपीजीसीएल – टाटा पावर – नीप्‍को – आईओसीएल- ईस्‍को - बीआरपीएल – ऑयल – बीसीपीएल – एनएचपीसी – एनपीजीसीएल



भारत हेवी इलेक्ट्रिकल्‍स लिमिटेड
पावर सेक्‍टर पूर्वी क्षेत्र
प्‍लॉट सं डीजे – 9/1सेक्‍टर ।। , करूणामयी, सॉल्‍टलेक सिटि , कोलकाता -700091, भारत
पंजीकृत कार्यालय -बीएचईएल हाउस , सिरि फोर्ट , नई दिल्‍ली -110049

पिछला अद्यतन दिनांक: 05/01/2016